Route 46 Corridor Improvements (Whitley 2A) |
Description: Near Paso Robles, from 0.1 mile east of Almond Drive to 0.8 mile east of McMillan Canyon Road. Convert to a 4-lane expressway.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Luis Obispo |
City | |
Zip Code | 93446 |
Senate District |
15 |
Assembly District | 33 |
Congressional District | 22 |
Caltrans District |
05 |
County/State Route | San Luis Obispo 46 |
Postmile Begin/End | 41 46.3 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 2425 | |
Lane Miles Added (HOV) | 0 | |
Lane Miles Added (Mixed) | 11.2 | |
Peak Period Time Savings (minutes) | 164164 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Department of Transportation | John Luchetta | (805) 549-3175 | john.luchetta@dot.ca.gov | |
Design (PS&E) Phase |
Department of Transportation | John Luchetta | (805) 549-3175 | john.luchetta@dot.ca.gov | |
Right of Way Phase |
Department of Transportation | John Luchetta | (805) 549-3175 | john.luchetta@dot.ca.gov | |
Construction Phase |
Department of Transportation | David Rasmussen | (805) 549-3677 | david.rasmussen@dot.ca.gov | |
Corridor System Management Plan |
Department of Transportation | John Luchetta | (805) 549-3175 | john.luchetta@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
CMIA |
$47,000 | $-1,912 | $45,088 | ||||
Non-bond Funding | |||||||
State/Federal* |
$9,000 | $-1,529 | $7,471 | ||||
Local** |
$3,000 | $0 | $3,000 | ||||
Total**** | $59,000 | $-3,441 | $55,559 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$0 | $0 | $0 | $1,538 | |||
Design(PS&E) |
$6,000 | $-1,529 | $4,471 | $4,538 | |||
Right of Way |
$6,000 | $0 | $6,000 | $3,770 | |||
Construction |
$47,000 | $-1,912 | $45,088 | $43,492 | |||
Total* | $59,000 | $-3,441 | $55,559 | $53,339 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
01/01/1998 05/01/2006 |
06/30/2011 |
01/01/1998 05/01/2006 |
100 | 01/01/1998 05/19/2006 |
0 -1 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2008 03/01/2012 |
|
07/01/2008 03/01/2012 |
100 | 07/01/2008 02/16/2012 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
05/06/2009 11/06/2012 |
|
05/06/2009 01/06/2012 |
100 | 05/08/2009 01/06/2012 |
0 0 |
|
Begin Construction Phase
End Construction Phase |
08/08/2012 09/08/2015 |
|
08/08/2012 09/08/2015 |
100 | 05/18/2012 08/15/2016 |
3 -11 |
|
Begin Closeout Phase
End Closeout Phase |
09/08/2015 06/15/2016 |
|
09/08/2015 06/15/2016 |
50 | 08/15/2016 01/12/2022 |
-11 -68 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 06/01/2009 | 06/01/2009 | 0 | 0 | |||
Implementation Date | 07/01/2009 | 07/01/2009 | 0 | 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 2425 | |
Lane Miles Added (HOV) | 0 | |
Lane Miles Added (Mixed) | 11.2 | |
Peak Period Time Savings (minutes) | 164164 |
Bond Funding Cost | |
---|---|
Adopted: |
$47,000,000 |
Current Approved: |
$45,088,000 |
Actual Expenditures: |
$42,465,000 |
Status as of December 31, 2023.